The motor box and lock fixtures, have to be placed as the transit is
delivered, to ensure functionality and safety. Fixtures for pendles can
be placed freely as long as it complies with the construction of the
system. See measure sketch below.
It is very important that the thickness of the wall is controlled
in advance.
When installing the transit coupling it is very important that the
motor box is placed in the room where it was intended when
it was ordered, because the entire system is constructed under
consideration of where the motor box is placed.
Installation with pendles is described in chapter 3.2.2 Concrete
Ceiling with Suspended Ceiling, page 14.
Measure sketch for transit coupling
3.10.3 Installing and connecting control button and
power supply
1586749-B
See the measure sketch below for further information.
Installation of the transit coupling is only possible using pendles. The
coupling can therefore only be installed where ceiling mounting is
possible.
The best result is obtained in a concrete ceiling.
When installing in wooden ceilings, it is very important that the
traverse system and coupling are installed in a way that they bend
down equally and with minimum bending.
If it is necessary to strengthen the ceiling in a wooden ceiling
construction, make sure to strengthen with a connected construction
between rail system and transit coupling.
Do not install the pendles in different rafters because this way the
coupling and traverse system will not bend down equally and the
coupling will not work correctly.
Before connection of the control button and power supply, it is
necessary to dismount the covers on the motor box. The covers are
dismounted by loosening the two screws, which holds each cover and
pulling the covers horizontally to the side.
The control switch is mounted in the room and at the height, the user
prefers. The control switch is opened with tools, and the back side is
mounted on the wall using two screws Ø3.5x30 mm.
The wire is shortened to a suitable length and connected to the
motor box. See drawing pos. A.
The power supply is mounted on the wall, visible or hidden, depending
on what is most suitable. The power supply is mounted on a Ø3.5x30
mm screw on the wall, using the "key" hole on the back side of the
power supply.
At the bottom of the power supply there is hole for a Ø3.5x30 mm
screw which makes it possible to lock the power supply on the wall.
The wire is shortened to a suitable length and connected to the
motor box. See drawing pos. B.