Commissioning and Operation

No changes may be made to the configuration and hardware
during operation!
6.1

Making presettings

The following presettings have to be made:
W

Assigning the valve supply on the bus coupler with M12 plug

(only for bus coupler with M12 plug)
W
Setting the diagnostic messages
All of these settings are made using the switch beneath fittings
A and B.
Proceed as follows for all of the presettings:
1. Remove the appropriate fitting.
2. Adjust the corresponding setting as described below.
3. Screw the fitting back in (0.6 + 0.2 Nm). Pay attention that the
sealing rings are positioned correctly.
6.1.1
Assigning the valve supply on the bus coupler
with M12 plug
The S4, S5, S6, and S7 switches for assigning the valve supply
are located beneath PG fitting B (see Fig. 6). The following is
assigned to each switch:
W
4 double subbases for double solenoid valves with solenoids
12 and 14 or
W
8 double subbases for single solenoid valves with
solenoid 14.
Commissioning and Operation
87