02 - Installation
The connection of the sensor for the Load Balancing function requires installation by a professional technician.
Note: Only one Power Manager can be installed downstream of a meter. In installations with multiple chargers, the Power
Manager must be connected only to the first charger added to the network. The remaining chargers should be added to
the network afterward and wired according to the scheme in Chapter 2.4.
02.1 - Package contents
The package includes:
1. Current sensor (1x for single-phase version and 3x for three-phase version);
2. CT box control board;
3. Shielded RJ45 connectors with bend protection (2x).
02.2 - Preparation for installation
Required but not included in the package:
- Network cable for connecting the CT box to the charger.
- Faston connector (female) and cable for grounding.
6.