Connection Of Pressure Line; Electrical Installation; Mains Power Supply; Inputs And Outputs - Ecolab Elados EMP KKS E10 Notice Technique

Masquer les pouces Voir aussi pour Elados EMP KKS E10:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

7.1.3

Connection of pressure line

Fig. 7.6
CAUTION
Observe max. permissible operation pressure of metering hose/pipe!
After 24 hours of operation, the metering head screws should be screwed down diagonally to
NOTE
3 - 4 Nm.
CAUTION
The metering pump head may contain residual water from the production tests.
7.2

Electrical installation

7.2.1

Mains power supply

Connect the mains power supply cable to the power grid.
7.2.2

Inputs and outputs

Fig. 7.7
The inputs and outputs in are equipped with protective caps in the as-delivered condition.
These caps must be removed when necessary (Pos. I-III).
NOTE
ATTENTION
417101338_EMPKKS.doc
Since the protective caps or connector plugs are coded, the respective images must be
observed (I-III). Do not use force when inserting them.
To protect the electronics against contact with chemicals or humidity, never operate the
metering pump without protective caps or connector cables, since the connectors can
become oxidized.
Mixing up the protective caps may result in malfunctions of the pump and/or damage to
the connectors!
Cut off the metering hose or pipe straightly.
Push over the union nut (pos. 2) and
crimping ring (pos. 3).
Attach the hose or the pipe onto the
connection piece (pos. 4) until the stop
motion and screw it up by hand.
Adjust angled position by loosening and
screwing down the nut again (pos. 1).
49