Start up

1.
Ensure that the metering line is not shut off at any place.
2.
Venting (see
function).
5.3

Setting back-pressure (pressure holding)

The back-pressure is adjusted to 1 bar + 20%, on the manufacturing side.
If a different pressure is required, the adjustment can be done as follows:
1.
Remove the sealing plug (Pos. 10) at the pressure holding operation button (Pos. 2)
either manually or with a small screwdriver.
2.
Disengage the screw (Pos. 11) and remove the operation button.
3.
Pull out the adjustment button (Pos. 12) slightly and set the desired counter pressure
by turning (right stop approx. 1 bar, left stop approx. 0.5 bar).
4.
Then fixate the adjustment button by pushing it back in, replace the operation button,
tighten the screw and insert the sealing plug.
Fig. 2: Setting back-pressure (pressure holding)
2
Operation button
10 Sealing plug
Ä Chapter 4.1 'Functional Description' on page 20), section c) Vent