Decommissioning, disassembly, environmental protection

Personnel:
DANGER!
Risk of injury due to the disregard of the specified personal protective
equipment (PPE)!
For all disassembly work, please respect the use of the PSA which is specified
on the product data sheet.
11.1

Shut-down operations

DANGER!
The procedures described here may only be carried out by skilled personnel as
described at the start of the chapter, this may only be done using PPE.
To take the equipment out of operation, proceed as follows:
1.
Before carrying out any subsequent work, completely cut off the electrical supply first
and secure it against unintentional switch-on.
2.
Relieve internal pressure of the pump and line pressure in the metering system.
3.
Drain off metering medium from the entire system without leaving any residue.
4.
Drain and remove operating and auxiliary materials.
5.
Remove the remaining processing materials and dispose of them in an
environment-friendly way.
MyControl - Shut-down operations
1.
Shut off the water supply.
2.
Turn the main switch to the "OFF" position (
on page 22, Fig. 1, Pos. 3).
3.
Turn off the main fuse (
Decommissioning, disassembly, environmental protection
n
Manufacturer
n
Production supervisor
n
Operator
n
Mechanic
Ä Chapter 4.1 'Construction' on page 22, Fig. 2, Pos. 1).
Ä Chapter 4.1 'Construction'