Before the photovoltaic system is connected, the solar array tension must be verified to make
sure that it is correct.
Never move the inverter when the solar array is connected. If it's necessary disconnected the solar
array first (see general conditions).
Caution: Because this inverter is non-isolated, only two types of PV modules are acceptable: mono
crystalline and poly crystalline. To avoid any malfunction, do not connect any PV modules that may
introduce leakage current to the inverter. For example, non-grounded PV modules will cause leakage
current to the inverter. See manufacturer technical datasheet of the PV modules.
Step 1: Check the output voltage of PV array modules, which has to be within the range of operation
of the IMEON (380 Vdc – 750 Vdc).
FR
FR
EN
WARNING: Exceeding the maximum input voltage can damage the unit! Check the system
before wire connection.
Step 2: Check the polarity of the PV string and identify the positive input (+) and the negative input (-).
Step 3: Switch the DC breaker of the PV to OFF position.
Step 4:
Wiring of the supplied connectors.
102
IMEON 9.12
DC + connector
Guide de montage / Installation guide IMEON 9.12 – Rev A.8
DC – connector