Commissioning; Before Switching On - Lenze 8200 vector Instructions De Montage

Masquer les pouces Voir aussi pour 8200 vector:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

7

Commissioning

Before switching on

(
Stop!
Special commissioning procedure after long−term storage
If controllers are stored for more than two years, the insulation resistance of the
electrolyte may have changed.
Possible consequences:
During initial switch−on, the DC−bus capacitors and hence the controller are
ƒ
damaged.
Protective measures:
Form the DC−bus capacitors prior to commissioning. Instructions can be found on the
ƒ
Internet (www.Lenze.com).
)
Note!
Do not change the switch−on sequence.
ƒ
In the event of a fault during commissioning please see the chapter "Troubleshooting
ƒ
and fault elimination".
In order to avoid personal injuries or material damage, check the following before connecting the
mains voltage:
ƒ The wiring for completeness, short circuit, and earth fault
ƒ The "emergency stop" function of the system
ƒ The motor circuit configuration (star/delta) must be adapted to the output voltage of the
controller.
ƒ If no function module is used, the FIF cover has to be fitted (delivery status).
ƒ If the internal voltage source X3/20, e.g. of the standard I/O is used, terminals X3/7 and X3/39
have to be bridged.
EDK82EV113 DE/EN/FR 11.0
l
Commissioning
Before switching on
7
135