2. If necessary, switch on the solar generator via the
external optional DC disconnect switch.
The power unit for the string inverter is switched on.
The AC and DC networks are switched on.
The string inverter only requires the AC grid for
commissioning and communication. Therefore,
commissioning and communication with the device
are also possible without solar generator power, e.g.
at night.
The following 3 options are available for
commissioning:
With the e.Key: See chapter Starting up the string
inverter using the e.Key, p. 85
Manually (gesture control): See chapter Starting up
the string inverter by hand (gesture control), p. 86
With e.Data: See chapter Starting up the string
inverter using e.Data, p. 89
6.2

Switching on the device

Procedure
1. Move the service switch on the string inverter from
0 to 1.
6.1:
Service switch
The string inverter is switched on.
The start screen appears: