Bosch BPT-S 3 Manuel De Service page 181

Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

English
Bosch Power Tec GmbH
(1)
5.4:
Connection of three string inverters to different
phases of a grid connection
[1]
PV system
[2]
String inverter
[3]
Control cabinet
[4]
Public power grid
Please note the following here:
Observe the applicable standards as well as the
local connection conditions from your grid operator
(permitted phase imbalance)
Fuse each string inverter separately: Using a
dedicated circuit breaker (automatic circuit
breaker) for each one
(2)
L1
(3)
L2
L3
Bosch BPT-S 3 / 3.68 / 4 / 4.6 | Operating manual
Installation | 63
(4)

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Bpt-s 4.6

Table des Matières