Installation and operating manual
9

Dismantling

Risk of injury through stabs and cuts!
Broken wires in the wire rope can result in protruding wires! Protruding wires can cut through safety gloves!
Wear suitable leather protective gloves when working with wire ropes.
Never let the wire rope run through your hands.
Lower the load lifting equipment and remove if necessary.
Press the DOWN button and pull the wire rope out of the hoist.
Danger of death due to electric shock!
Disconnect the hoist from the power supply by pulling out the plug.
Illustration 31
Pull out the power plug.
Whilst lowering wind up the wire ropes (1) in the correct position or onto a reel to ensure that there are no loops (2), which would
make the wire ropes unusable.
Loosen the anchorage of the hoist.
Dismantle the diverter pulleys and load bearing points.
10

Shutting down

10.1 Work breaks

The workplace must be secured as follows during work breaks:
Put the load lifting equipment on the ground or cordon off the area beneath the suspended load.
Disconnect the power supply and secure the hoist against unauthorized use.

10.2 Temporary shutdown

If the hoist is not required for several days or weeks but should remain mounted in the same position and location, the hoist must be
secured as follows: