3.4 Smart Meter Installation

1. The energy meter must be installed between the IMEON inverter and the Public Grid. The
monophase Smart meter model is equipped with a clamp. See the diagram below:
FR
2. The communication cable has to be plugged on the RS485A inverter port.
FR
Follow the pin map below to establish the communication between the energy meter and the
EN
inverter.
The length of the cable between the inverter and the meter must be a maximum of 10 to 20m
depending on the cable category used. In case a longer cable used, please refer to the standard
IEA-485 and the guideline TSB-89.
3. To confirm the good communication between the inverter and the Smart Meter, please connect to
MANAGER WEB and check if the following symbol
60
IMEON INVERTER
Manuel d'installation / Installation guide IMEON Inverter – Rev B.5
is displayed on the top left of the interface.