3.4 Smart Meter Installation

1. The energy meter must be installed between the IMEON inverter and the Public Grid.
Remark : The monophase Smart meter model is equipped with a clamp.
Clamp has white and black cables. Color code and arrow direction (→) must be respected as defined
below.
2. The communication cable has to be plugged on the RS485A inverter port.
Follow the pin map below to establish the communication between the energy meter and the
inverter.
The length of the cable between the inverter and the meter must be a maximum of 10 to 20m
depending on the cable category used (stranded cable of minimum category 6A is recommended).
In case a longer cable used, please refer to the standard IEA-485 and the guideline TSB-89.
Note : Image on left is only for illustration purpose (wiring following code T568B) and may differ from our current
3. To confirm the good communication between the inverter and the Smart Meter, please check if the
orange AND green LEDs of the RS485A port are flashing.

3.5 Ground connection

WARNING: It is necessary to connect the frame of IMEON to the earth ground in order to
prevent the electric shock.
installation.
For wiring, ignore cable colors and use only pin numbers.