3. Electrical Installation
1. Pump wiring: The motor must be connected to the ter-
minals L1, L2, L3 and GROUND. Observe rotation direction.
2. Accessories wiring: Connect a source low sensor to
terminals 1 and 2 (required), remote control switches to
terminals 3 and 4, water detection sensor for surface pump
to terminals 5 and 6, SunSensor module to terminals 7
and 8, analog sensors to terminals 9 and 10 or 11 and 12,
water meter to terminals 13 and 14.
3. DC input wiring: Connect the positive terminal of the
PV array to +, the negative terminal to −. Observe max.
input voltage.
4. Grounding: A protective earth connection must be
wired to GND
.
4. Pump Installation
Submersible pumps: Lower the pump into the water
source with caution, use a safety rope.
Surface pumps: Install the surface pump on an adequate
foundation with sufficient pipe sizing to ensure efficient op-
eration. Fill the pump with clean water prior to starting it.
For detailed information refer to "9.2.1 Wiring the pump"
on page 39.
For detailed information refer to "8.5.6 Pump Accessories
Wiring" on page 31.
For detailed information refer to "8.1 General" on page
18.
For detailed information refer to "8.6 Grounding" on page
33.
For detailed information refer to "9.2 Submersible Pumps"
on page 39.
Depending on your pump system, refer to "9.2 Submersible
Pumps" on page 39 or "9.3 Surface Pumps" on page
51 for detailed information.

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Psk2-9Psk2-15Psk2-21Psk2-25Psk2-40

Table des Matières