Télécharger Imprimer la page

Salicru SLC CUBE 3+ PS Mode D'emploi page 128

Publicité

Les langues disponibles

Les langues disponibles

OFF (the auxiliary contact of the output switch in the
output panel board has to be connected according to
the instructions of section 5.2.9.2.).
If the following alarm message appears on the LCD Control
Panel ...
MAINS PHASE ROT.
... also an audible alarm will beep in each equipment with the
message in the screen and the affected UPS/s not be able to
be started up, due to the wrong input phase rotation.
If it happens in only one UPS of the parallel system, turn
ˆ
«Off» the input switch (Q1a) of the corresponding equip-
ment and the one in the switchgear panel board. Swap
two phases of the input terminals of the UPS leaving the
connections in the same order as the rest of the equip-
ments and repeat the start up procedure described up
to now.
If it happens in all equipments of the parallel system,
ˆ
turn «Off» the input switch (Q1a) of each UPS and input
switches of the switchgear panel board, swap two
phases in the input terminals of the switchgear panel
and repeat the start up procedure described up to now.
In equipments or systems with separate static bypass line SLC
CUBE3+ PS B:
Turn the bypass switches from panel board «On».
Turn the bypass switches (Q4a) of each UPS to «On».
CONTROL & STATUS
OF THE UNIT
screen 1.0
Fig. 44. Diagram, start up/shutdown procedure.
128
UPS START INH.
screen 4.*
()
UPS ON STAND-BY
()
<ENT> TO START
screen 1.1
(ENT)
<ENT> TO CONFIRM
(ESC)
<ESC> TO CANCEL
screen 1.2
(ENT)
UPS RUNNING
<ESC> TO STOP
screen 1.3
(ESC)
<ENT> TO CONFIRM
(ESC)
<ESC> TO CANCEL
screen 1.4
(ENT)
If the following alarm message appears on the LCD Control
Panel ...
BYPASS PHASE ROT.
... also an audible alarm will beep in each equipment with the
message in the screen and the affected UPS/s will not be able
to be started up, due to the wrong bypass phase rotation.
If it happens in only one UPS of the parallel system, turn
ˆ
«Off» the bypass switch (Q4a) of the corresponding
equipment and the one in the switchgear panel board.
Swap two phases of the bypass terminals of the UPS
leaving the connections in the same order as the rest of
the equipments and repeat the start up procedure de-
scribed in the three previous steps.
If it happens in all equipments of the parallel system,
ˆ
turn «Off» the bypass switch (Q4a) of each UPS and
bypass switches of the switchgear panel board, swap
two phases in the bypass terminals of the switchgear
panel and repeat the start up procedure described in the
three previous steps up to now.
()
BATTERY TEST
()
<status>
screen 1.5
Screens 1.1 and 1.3 are alter-
nated in the diagram, depen-
ding on the status of the
equipment.
The same happnes with the
screens1.6 and 1.8. Depen-
ding on the Smart Eco-mode
status, they are swapped.
UPS START INH.
screen 4.*
()
SMART ECO-MODE
()
<ENT> TO ACTIVE
screen 1.6
(ENT)
<ENT> TO CONFIRM
<ESC> TO CANCEL
screen 1.7
(ENT)
SMART ECO-MODE
<ESC> TO DEACTIVE
screen 1.8
(ESC)
<ENT> TO CONFIRM
(ESC)
<ESC> TO CANCEL
screen 1.9
(ENT)
(ESC)
SALICRU

Publicité

loading