Picture 13 – Inverter start-up
3)
As the inverter is correctly started-up, close the bypass switch SBCB when indicated by the
display. The logic will check the correctness of the bypass phase sequence and RMS
voltage value.
Picture 14 – Bypass start-up
4)
Close the battery switch BCB when indicated by the display.
44
OMP06262 REV. E
Installation and start-up of KEOR HPE UPS 200-250-300 kVA
Installation et démarrage de l'ASI KEOR HPE 200-250-300 kVA
Installazione e avviamento KEOR HPE UPS 200-250-300 kVA