user needs to mesaure any phase of the 3 phase, then
clamp them to that phase's conductor.
3. The connecting method of 3 phase 4 wires and 3 phases
3 wires, see figure 6 and 15
4. Press SEL to choose one of the three phases, see figure
21.
The double display shows the value of tested object's
active engergy kWh value and the measuring time of the
corresponding phase.
The measuring reading gets increasing along with the
time increases. Press HOLD to read a particular time kWh
value. Then the reading and time are locked, but still
continuous accumulate measuring time.
After read the data, press HOLD again to continous
measurement. kWh value continous accumulate and the
measuring time jumps to the present measuring time.
When the measuring time is over 24 hours or the Meter
is switched to other measuring ranges, active energy
measuring will stop.
The maximum readinng of acitve energy is 9999kWh.