6 Commissioning

6 Commissioning
DANGER
Risk of injury due to unexpected start-up
The following instructions must be followed during all maintenance, servicing, assembly, disassembly, and repair work:
• Switch off the power source.
• Disconnect all electrical connections.
WARNING
Electric shock
Dangerous voltage due to defective cables.
• Check all live cables and connections for proper installation and damage.
• Replace any damaged, deformed or worn parts.
NOTICE
• Please take note of the following instructions:
 3 Product description on page EN-4
• The system may only be installed and commissioned by qualified personnel (in Germany, see TRBS 1203).
• Components must only be used in environments with sufficient ventilation.
• The interconnection (serial or parallel connection) of several power sources may result in material damage.

6.1 Attaching the MasterLiner

NOTICE
• Ensure the MasterLiner is the correct length.
• Avoid bending the MasterLiner unnecessarily when it is laid. Laying in a cable carrier is essentially possible.
However, breaches of the minimum bending radii can cause damage and wire feed irregularities. Note the bending
radii for use when dynamically laying the MasterLiner:
 3.2 Suspension/total bending angle of all bending radii on page EN-7
• When suspending MasterLiner of any type, use suitable mounts, strain relief devices for the wire feeder and wire
drums as well as the total wire feed distance.
The section below presents and describes the installation using a QC quick connector.
EN - 10
MasterLiner Maxi Flex/HD; Basic Flex/HD
BAL.0510.0 • 2021-08-19

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Masterliner basic flex/hd

Table des Matières