• Feed the cable through the empty pipes in the
foundation before the columns are set up. Then
move the columns to the installation location.
Place the cables through the holes in the base-
plate and guide them through the column to the
column head. Carefully place the columns up-
right to prevent kinking or clamping.
• Connect the cables according to the drawing
(Figure 24).
• When merging the cable connections at the
head plate, ensure that the cable does not con-
tact rotating parts.
• Pay particular attention to secure contact of the
plug connections.
Figure 24: Cable path without using riser and cross-pipe
8.3

Lifting arm assembly

Hang in the standard lifting arm and then place an
acid-free multi-purpose grease into the joint bolts in
each case from above into the hole and then insert
the enclosed locking ring.
The lifting arm bolts must be secured
on both sides as otherwise a reliable
connection is not given between the
lift rails and lifting arm.
OPI_SMART LIFT 2.30 SL-2.35 SL-2.40 SL_V3.1_DE-EN-FR-ES-IT
8.4
Mounting the safety bar on the shorter
lifting arms
Assembling the safety bar is done on the left and
right short lifting arm (see the following images).
Procedure:
1. Hang in the safety bar at the end of the pusher
piece. (Figure 25)
Figure 25
2. Guide the V-shaped clamp between the pull
strap and web plate.
3. Hit the clamp with a tool until it bends. (Figure 26)
Figure 26
4. Check for proper seating of the safety bar.
8.5

Commissioning

Before commissioning, a single safety inspection
i
must be done (use the "single safety inspection"
form)
If the lift set up is done by a specialist (factory
trained assembler) then he can also do the safety
inspection. If the set up is done by the operating