ICAR PQS
1.6
Inserzione completa su MT - Full MV wiring configuration - Installation complète en moyenne tension
INSERZIONE CON MISURE E RIFASAMENTO SU MT
Misura tensione
Misura corrente
Angolo di sfasamento
Sovraccarico condensatori
Impostazione parametri
CONFIGURATION WITH MV MEASUREMENT AND CORRECTION
Voltage measure
Current measure
Phase angle offset
Capacitor overload current measure
Parameter setting
INSTALLATION COMPLETE EN MOYENNE TENSION
Mesure tension
Mesure courant
Angle de déphasage
Mesure surcharge condensateurs
Définition paramètres
3 misure di tensione concatenata L1-L2, L2-L3, L3-L1 su media
tensione
Fasi L1-L2-L3 su media tensione
90°
3 misure calcolate su L1-L2, L2-L3, L3-L1
P02.03 = Trifase
P02.04 = L1-L2-L3
P02.06 = L1-L2-L3
3 ph-to-ph voltage reading L1-L2, L2-L3, L3-L1 on MV side
L1-L2-L3 phase
90°
1 reading on L1-L3, LV side
P02.03 = Three-phase
P02.04 = L1-L2-L3
P02.06 = L1-L2-L3
3 mesures de tension entre phase L1-L2, L2-L3, L3-L1 en moyenne
tension
Phase L1-L2-L3
90°
3 mesures calculées sur L1-L2, L2-L3, L3-L1
P02.03 = triphasé
P02.04 = L1-L2-L3
P02.06 = L1-L2-L3
80 / 86
rev8 may18
P02.22 = MT
P02.23 = ON
P02.22 = MV
P02.23 = ON
P02.22 = MV
P02.23 = ON