Assembling the frame, SA0 (single-pipe)
versions
The ultimateSAM version SA0******* distributors are supplied with a frame
to be assembled, which comprises the following components:
manifold with support flange
upright
flange gasket
upright o-ring
fastening elements (screws)
To assemble the SA0 distributor, proceed as follows:
a.
place the upright into the opening on the manifold and align the holes
on the flange with those on the manifold.
b.
Fasten the flange to the manifold by tightening the screws to 7-8 Nm
(5-6 ft lb). Use the fastening elements supplied. Before assembly, make
sure that the o-ring is correctly inserted between the flange and the
manifold..
c.
Remove the plastic clamps on the upright insulation (only needed for
transport).
Fig. 1.g
c
Fig. 1.e
f
Fig. 1.f
O-ring
Fig. 1.h
Fig. 1.i

1.5 Inserting and attaching uprights

For a bottom feed distributor,
a.
Tilt the upright, inserting it into the retaining ring in the top bracket.
(Fig.1.J)
b.
Continue sliding the upright upward until the bottom of the upright
can be inserted into the hole in the bottom header.
c.
Using 7-8 Nm torque (5-6 ft lb), secure the flange of the upright to the
bottom header using the fasteners provided. Before tightening, check
to ensure the o-ring is in the proper position between the flange and
distributor. (Fig.1.k)
d.
Continue until all uprights are installed.
Fig. 1.j
For a top feed distributor,
a.
Check that the upper flange with o-ring is properly positioned on the
upright.
b.
Tilt the upright, inserting it into the gasket in the bottom header (Fig.1.l).
Note: if necessary, use water in order to insert upright into gasket;
c.
Continue sliding the upright downward until the top of the upright can
be inserted into the opening in the top header.
d.
Before tightening, check to ensure the o-ring is in the proper position
between the flange and distributor. (Fig.1.m)
e.
Using 7-8 Nm torque (5-6 ft lb), secure the top flange to the top header
using the fasteners provided.
f.
Continue until all uprights area installed.
Fig. 1.l