Installation Check-Up - LaCimbali M26 Utilisation Et Installation

Masquer les pouces Voir aussi pour M26:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

5. Installation Check-up

WARNING: AFTER INSTALLATION, CHECK TO SEE IF THE MACHINE IS WORKING PROPERLY (see the
Installation Module C)
WATER CONNECTIONS
No leaks from the connections or tubes
FUNCTIONING
Boiler and operating pressures are normal.
The pressure gauge is working properly.
The self-levelling device is working properly.
The expansion valves are working properly
WARNING: ONCE THE MACHINE HAS BEEN INSTALLED AND IS READY FOR USE, BEFORE ALLOWING
THE WORKER TO START USING THE MACHINE, WASH THE INTERNAL COMPONENTS ACCORDING
TO THE INSTRUCTIONS BELOW:
GROUPS
Hook up the lter holders to the groups (without coffee).
Let each group dispense water for about a minute.
HOT WATER
Continuously dispense hot water (pressing the appropriate button) until at least 5 liters of water have been used for
a machine with 2 groups, and 8 liters for a machine with 3 groups.
See the "Hot water dispensing" chapter in the User's Manual.
STEAM (also with Turbosteam)
Dispense steam from the nozzles for about a minute, using the appropriate buttons.
.
EN

Publicité

Chapitres

Table des Matières
loading

Ce manuel est également adapté pour:

997-184-000

Table des Matières