LEGRAND KEOR HPE 400 kVA Installation Et Démarrage page 43

Publicité

Les langues disponibles

Les langues disponibles

Installation and start-up of KEOR HPE UPS 400-500 kVA
Installation et démarrage de l'ASI KEOR HPE 400-500 kVA
Installazione e avviamento KEOR HPE UPS 400-500 kVA
Picture 14 – Battery start-up
Operation on BCB switch
The switch BCB, located in the external battery cabinet, can only be closed if the DC
voltage is in tolerance. Serious damages both to the battery and the equipment may
occur if the breaker is closed before the front panel requires it.
5)
Close the UPS output switch OCB to connect the UPS to the load bus. After this operation
the start-up is completed and the display will show the final mimic diagram.
OMT87115 REV. B
43