Picture 12 – Inverter start-up
3)
As the inverter is correctly started-up, close the bypass switch SBCB when indicated by the
display. The logic will check the correctness of the bypass phase sequence and RMS
voltage value.
Picture 13 – Bypass start-up
4)
Close the battery switch BCB when indicated by the display.
42
OMT87115 REV. B
Installation and start-up of KEOR HPE UPS 400-500 kVA
Installation et démarrage de l'ASI KEOR HPE 400-500 kVA
Installazione e avviamento KEOR HPE UPS 400-500 kVA