Installation and start-up of KEOR HPE UPS 100÷160 kVA
Installation et démarrage de l'ASI KEOR HPE 100÷160 kVA
Installazione e avviamento KEOR HPE UPS 100÷160 kVA
Mains connection
The connection to the mains must be carried out with protection fuses between the
mains and the UPS.
The use of differential protection devices in the line supplying the UPS is
unadvisable. The leakage current to ground due to the RFI filters is rather high
and it can cause spurious tripping of the protection device.
According to CEI EN62040-1 standard, in order to take into account the UPS'
leakage current, residual current devices having adjustable threshold can be used.
Mains connection
Include an appropriate and readily accessible disconnecting device in the
electrical line connecting the UPS to the mains.
4.1
CONNECTION OF THE POWER CABLES
For the electric connection of the KEOR HPE UPS 100÷160 kVA, connect the following cables:
 DC supply from the battery (if the battery is external);
 AC supply from the rectifier and bypass supply mains;
 AC output to the loads.
Injury hazard due to electric shock!
Very high voltages are present at the ends of the cables coming from the battery:
 Isolate the battery via DC circuit breakers before connecting it to the UPS;
 Connect the ground cable to the relevant bar before carrying out any other
connection inside the device.
Risk of damages to the device due to insufficient insulation
 The cables must be protected from short-circuits and leakage currents to earth;
 The connection points must be hermetically sealed to prevent the air from
being sucked through the cable passage.