Functional Check of the Flow Control Device

For the functional check proceed as follows:
 Remove the cover.
 Unscrew the knurled nut (see Fig. 6.1, pos. 3) from the eccentric and remove the
complete eccentric from its holder on the hydraulic motor.
 Press the ON/OFF (I/0) switch. Approx. 10 seconds after the unit has been started, it
should change to fault mode (the red LED is permanently ON).
 Refit the eccentric.
 Press the ON/OFF (I/0) switch to reset the unit.
 Press the ON/OFF (I/0) switch again (unit starts metering).
 Slowly reduce the supply of fresh water to reach 0 MPa (0 bar) of pressure.
When the pressure falls below 1.4 MPa (1.4 bar) the unit changes to fault mode
(red LED is permanently ON).
 Reopen the fresh water supply.
 Press the ON/OFF (I/0) switch to reset the unit.
 Reposition the cover.
6.2.5

Changing over to a New Product

When changing over to a new product, make sure to thoroughly flush the suction pipe,
the metering pump, and all lines in contact with the product before you connect the new
supply container.
If products are used which contain glucoprotamine (e.g. INCIDIN PLUS), the O-rings on
ATTENTION
the piston and on the piston rod need to be replaced by EPDM O-rings.
If products are used which dont contain glucoprotamine, the O-rings on the piston and
on the piston rod need to be replaced by SILICONE O-rings
(see chapter
To change over to a new product, proceed as follows:
 Fill an appropriate vessel with water and immerse the suction pipe
 Flush suction pipe, metering pump, and the lines in contact with the product as follows:
 unscrew the flow control device (see Fig. 3.2, pos 12), insert the sealing plug, and
place the flow control device in an appropriate vessel,
 unscrew the knurled nut (see Fig. 6.1, pos 3) from the eccentric and pull the eccentric
from its holder on the hydraulic motor,
 manually move the piston rod (see Fig. 6.1, pos 7) forth and back until clear water
without product residues is running from the flow control device.
 Insert the suction pipe into the new supply container.
 Bleed metering pump until product running out of flow control device is bubble-free
(see chapter
 Push the eccentric back onto its holder and tighten the knurled nut.
 Remove the sealing plug and screw the flow control device in again.
 Check the unit for leaks and malfunctions.
 Set the concentration as described in chapter
as described in chapter
417101158_DG1.docx
2.3
„General Safety Information").
6.1
„Start-Up")
6.2.1
„Checking the Concentration Setting".
6.2
„Setting the Concentration" or check it