12 - MAINTENANCE PLAN
to ensure correct automation operation, it is necessary to perform
periodic maintenance on the same.
With the exception of the ordinary cleaning of the window, by the
Door not powered:
Check the stability of the automation and check the tightness of all the screws
Check the correct alignment of the panels and their stroke, if necessary act on the runners and limit
switches
Check the wear of the runner wheels
Check the correct tensioning of the belt
Clean the internal sliding track and the runner wheels
Clean the floor sliding runner
Clean the radars and photocells
Door connected to the power supply:
Check the correct operation of the command and safety devices (radar and photocells)
Check the stability of the doors: during operation they must slide smoothly and evenly, without fric-
tion and jolts
If present, check the correct operation of the electric lock and release
If present, check the condition of the batteries and correct functioning of the charging device
Check that the forces generated by the door comply with the requirements indicated in the current
standards (EN16005)
Every 1,000,000 cycles replace the belt, runners, gearmotor
and control unit.
The table shows the maintenance intervals referring to standard
owner, all maintenance activities must be carried out by a qualified
professional, who must respect the indications in the table below:
Operation
operating conditions: the installer can adjust the plan according to
the actual conditions of use and record the interventions carried
out in the maintenance register.
Frequency
Every 6 months or
every 500,000 manoeuvres
Every 6 months or
every 500,000 manoeuvres