The ceiling unit includes some components common to the "left-side" and "right-side" subassemblies.
During assembly, the bolt-inserting direction for one subassembly should be opposite to that for the other so that the
nuts are located inside when the Plasma Display is installed.
(In this manual, the procedures of assembling the "right-side" subassembly when viewed from the front of the
Plasma Display are shown in the figures below.)
Preparation of components
Preparation of M16 bolts (80 mm)
Install one plain washer
Preparation of M8 bolts (60 mm)
Install one spring washer

(60 mm)
Preparation of plates
As shown in the right figure, prepare 6 sets of plates
1. Insert insulating collars
them between plates .
2. Pass the accessories over the prepared M16 bolt
shown in the figure, and secure them using the nut
The bolt should be securely tightened to the torque given below.
(16~20 N•m)
Preparation of base
As shown in the right figure, prepare 2 sets of base
1. Insert insulating collars
2. Put the protective collar

3. While holding the collars, pass one prepared M16 bolt
through.
4. Fit washers on the bolt, and fasten in place with the nut
The bolt should be securely tightened to the torque given below.
(16~20 N•m)
Preparation of the bracket 1
As shown in the figure on the right, adhere two gaskets to each of
the brackets, and prepare each pair of brackets in this way.
(14 sets)
and one collar
in that order, on each M16 bolt (80 mm)
(22 sets)
and one plain washer
into the protective collar
into the protective collar
between the side plates of the base
, bracket 2
and bracket 3
in that order, on each M8 bolt
and bolts.
, and put
Prepared
M16 bolt
in the order
.
2
and bolts.

(E-2)
4
.
.
1
(E-2)
(E-1)
1
(E-1)
2
3
Prepared M16 bolt
19