Commissioning

6.1

Checklist

Commissioning shall be carried out by trained experts in accor-
dance with this user manual and as per applicable local and
national codes.
E-92
CAUTION!
Before commissioning the device, the
following requirements must be met:
• The device must not show any damage.
• When recommissioning the device after
a repair, a professional routine test in
accordance with EN 61010-1 must be
performed.
• Make sure that the device is configured in
accordance with the connected periph-
erals.
• All connected voltage and current sourc-
es must correspond to the technical data
of the device.
• Before commissioning you must provide
proof that the connection with other
equipment, such as a transmitter includ-
ing cables and wires, is permissible.
• The provisions of 60079-14 must be
observed.
• The specifications given in the EU-Type
Examination Certificate must be
observed.