Télécharger Imprimer la page

Kongskilde KDC 4000 Instructions De Service page 6

Masquer les pouces Voir aussi pour KDC 4000:

Publicité

Les langues disponibles
  • FR

Les langues disponibles

Installation:
The cleaner may be advantageously installed to
allow crop passage immediately after intake and
before discharge.
Location
Place the cleaner so as to allow space beside the
unit for necessary adjustments.
Do not forget to provide space for screen replace-
ment, i.e. about 1.5 m beside the unit. Screen re-
placement is most easily done from the right-hand
side of the combi cleaner (viewed from the inlet
end).
Direction of rotation
Wiring should be made for counter-clockwise direc-
tion of rotation of screen drum, fan and trough au-
ger (viewed from the inlet end).
Wiring diagram for the cleaner is placed in the con-
trol box.
6
Pipeline for blower
The blower pipeline should be of the Kongskilde
OK200 dimension. It is recommended to use as few
bends as possible and a cyclone at the end of the
pipeline.
At a commonly occurring content of impurities in the
crop, the fan is powerful enough to blow the trash
approx. 20 m (including 4 meters vertical length,
two bends and one cyclone).
If to much fan power is applied to conveying, this
will reduce the air flow and, accordingly, the
cleaning efficiency of the aspiration cleaner. If ad-
ditional conveying length is required, an extra fan
may be inserted.
Separation of screenings
The screenings may either be discharged through
a separate gravity outlet or delivered into the trash
blow line (A) and discharged together with the light
impurities.
B
A
90°
Cyclone
OK200 pipeline
90°
C

Publicité

loading