Gluing On Sealing Bands; Installing Slide-In Module With Extension Duct - AIT LD 30 BO Notice De Montage

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

9.4 Gluing on sealing bands

1. Glue sealing band [3.1] and [7] onto out-
side of duct end of fluid separator [3]
and/or onto outside of extension duct [5]
so that it terminates flush at the face end.
NOTICE
Damage to brickwork caused by conden-
sate if the sealing bands [3.1] and [7] are
fitted incorrectly. Glue in sealing bands
correctly.
9.5 Installing slide-in module with
extension duct
1. Produce fixing holes for the internal cover.
Use enclosed drilling template. Note the
TOP unit position. Insert dowel.
2. Slide extension duct [5] into wall sleeve
with centring ring(s) [4] and if necessary
[6] up to stop of external cover. Ensure
that the centring ring is positioned as far
inside as possible. If needed, fix centring
ring on wall sleeve with adhesive tape.
With LD 30 VS extension, use two centring
rings. The sealing band [7] must fit tightly
in the external cover.
3. Remove electronics compartment cover
(2 screws).
4. Use thin screwdriver to pierce cable grom-
met in internal housing.
NOTICE
Damage to unit from water ingress if the
connecting cable is incorrectly fed into
the internal housing or if the cable grom-
met is not fitted correctly. Pierce cap of
cable grommet [13] so that it can tightly seal
the power cable. The cable grommet must
be correctly attached in the housing.
If using LD 30 BK units and connecting
an optional button or switch, the second
input is used with the relevant grommet
 Figure.
5. Slide complete slide-in unit a little into the
wall sleeve with the internal cover. Guide
connecting cable(s) through cable grom-
met(s) into connection area.
6. Slide complete slide-in unit into the wall
sleeve with the internal cover until stop is
reached. Sealing band [3.1] must fit tightly
in extension duct.
7. Screw internal cover down to wall with 4
screws. Note the TOP unit position. Suita-
ble mounting material is to be supplied by
the customer.
8. Connect control cable to W-PPB
 Connection plans in Appendix.
9 Mounting | UK
33

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Ld 30 bkLds 45 oLds 45 k

Table des Matières