I. INSPECTIONS AND PREVENTIVE MAINTENANCE
In the event of work on the UV reactor, ensure that personnel are qualified and authorised.
RECOMMENDATIONS FOR VERIFYING OPERATION AND USE
The following points must be regularly checked in order to make sure that the UV reactor is operating
perfectly:
• Lamp operation check: Green light on
• UV intensity check: The display on the Millénium III monitor must show a value greater than
50%
In the event of a UV intensity fault (<50%); do not carry out the sensor calibration procedure
which must only be carried out with: new lamps(s), clean quartz, clean UV sensor
• Check the operation of the flowmeter: In the event of an interruption in flow (backwashing of
filters for example), the UV lamps must automatically turn off within 60 seconds, and restart 30
minutes after return to service. (See message on Millenium III display)
• Check the correct operation of electrical cabinet ventilators in order to avoid all risk of
overheating.
Check that the grills or filters are not obstructed.
• Activate the MANUAL cleaning device of the UV reactor on a daily basis
(Not applicable in the event of an automatic device: In this case make sure that the latter is
working)
• Checked the number of stop/starts of lamps on the Millénium III monitor display, which must be
coherent with the number and frequency of technical stoppages (filter backwashing, etc).
MP 030 EL NM GB
Marque, Modèles et Brevets déposés - Produits exclusifs
Copyright BIO-UV - 29/01/2009
Page 18

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Mp030 elMp030 nmMp030 es

Table des Matières