2.5

Accessories

2.5.1 Fixing accessories
Item
The purpose of the side cover set is to
integrate the collector in the existing roof cover.
The compensator is used to connect two
collectors incl. thermal insulation and
venting screw.
The pipe duct is used as a hydraulic
connection and is only used if more than five
collectors are installed next to each other.
The cover extension above each other is
required when two collectors are installed
above each other and is used to cover the
connections between the upper and lower
collector.
2.5.2 Solar heating system accessories
Item
Stainless steel corrugated hose, for the roof outlet/duct (2 hoses)
SOKI plus, solar compact installation
SOKI 6 plus, solar compact installation with integral control unit SOM 6 plus
SOKI 7 plus, solar compact installation with integral control unit SOM 7 plus
SAS SOKI cylinder connection set, for SOKI plus, SOKI 6 plus and SOKI 7 plus
SOKI SBK-M, solar compact installation for solar heating combi cylinder SBK 600/150
SOM 6 plus, temperature differential control unit for one consumer.
SOM 7 plus, temperature differential control unit for two consumers
SOM 6/3 D, temperature differential control unit for up to three consumers
SOM 8, comfort control unit
SOM SBK, control unit for solar heating combi cylinder SBK 600/150
H-30 L, heat transfer medium, 10 litre can
H-30 L, heat transfer medium, 20 litre can
Expansion vessel, 18 litres
Expansion vessel, 25 litres
Expansion vessel, 50 litres
SBB 300 plus, freestanding solar cylinder for DHW heating
SBB 400 plus, freestanding solar cylinder for DHW heating
SBB 600 plus, freestanding solar cylinder for DHW heating
SBK 600/150, solar heating combi cylinder
SBP 700 E SOL, buffer cylinder
SBB 400 WP SOL, freestanding cylinder for DHW heating by heat pumps in conjunction
with solar heating systems
26
Standard delivery
1 x left-hand end strip,
1 x right-hand end strip,
2 x roof outlets/ducts,
2 x compensators, 6 x sealing strips,
1 x collector sensor well, 1 x bracket,
6 x clips, seals and screws.
1 x compensator with venting screw,
2 x seals.
Compensator, bracket, nuts, gaskets.
1, centre cover, 2 x centre side cover,
1 x cover holder, screws and washers.
2.6

Installation

 
The solar heating system must only
!
be filled with H-30 L or H-30 LS
heat transfer medium to provide protection
Part no.
against frost and corrosion (Section 2.11).
22 13 64
If more than 30 collectors are linked together
to form a single hydraulic group, the current
type-test qualification is invalidated. Larger
systems require an individual approval.
17 08 04
Commercial systems, the open content of which
exceeds 10 litres and not more than 50 litres
(6 to 30 collectors), require notification to the
22 13 65
relevant local authority [in Germany – check
local regulations].
22 13 72
Pipework installation
The pipes for flow and return lines must be
made of copper or stainless steel or should be
corrugated stainless steel hoses.
Recommended pipe diameter
- up to 4 collectors: Ø 18 x 1
The pipes routed to the interior of the building
Part no.
are to be provided on site. Ventilation tiles are
07 34 69
recommended as roof outlets for tiled roofs with
22 04 58
more severe inclination; for flat and corrugated
22 04 59
roofs with lesser inclinations, routing the pipes
through an external wall is recommended.
22 04 60
Avoid sawing off pipes (swarf). It is advisable
22 04 63
to use a pipe cutter for swarf-free cutting.
07 42 43
The pipes installed should be connected to an
22 04 62
earthing system in accordance with current
22 04 61
regulations. All pipes must be connected to the
07 32 23
building earthing system via a short connection.
07 43 50
Soldered lines
07 41 71
Soldered lines must be brazed. Please follow
07 32 21
DVGW Code of Practice GW 2 when carrying
07 32 22
out this work. The solder used must comply
07 40 30
with DIN EN 1044: CP105 and CP203, both are
07 40 31
used without flux. Only gunmetal and brass
18 78 68
fittings are to be soldered using flux F-SH- 1
18 78 73
in accordance with DIN 8511. Other flux
would have a detrimental effect on corrosion
18 78 74
resistance.
18 78 75
07 40 67
Alternative lines
18 54 60
Appropriate sealant must be used on lines
18 55 21
using threaded locking ring fittings, press
fittings and corrugated hoses. The seals
should be resistant to glycol and temperatures
up to 180 °C.
Roof outlet/duct
Two flexible stainless steel corrugated tubes
that can be mounted on the threaded collector
connections or collector sensor well with flat
packing and union nuts are used to connect
the collector array to the pipework. These
roof outlets/ducts are equipped with factory-
fitted thermal insulation that is resistant to
temperature and UV.

Publicité

Table des Matières
loading

Table des Matières