Making The Electrical Connection; Connection Diagrams; Zero Point Adjustment - WIKA PSD-30 Mode D'emploi

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

6. Commissioning, operation

6.2 Making the electrical connection

The instrument must be earthed via the process connection!
The power supply for the pressure switch must be made via an energy-limited electrical circuit in
accordance with section 9.3 of UL/EN/IEC 61010-1 or an LPS to UL/EN/IEC 60950-1 or class 2 in
accordance with UL1310/UL1585 (NEC or CEC). The power supply must be suitable for operation
above 2,000 m should the pressure switch be used at this altitude.
For cable outlets, make sure that no moisture enters at the cable end.

Connection diagrams

Circular connector M12 x 1; 4-pin
Assignment
U
U -
S
+
1
3
2

Zero point adjustment

Check the indicated zero point on the display during commissioning.
Should an offset be displayed as a result of installation, this can be reset in programming mode with the
0SET parameter
Carry out zero point adjustment for relative and vacuum pressure measuring ranges in a
depressurised state.
Carry out zero point adjustment of absolute pressure ranges from 0 bar absolute
(vacuum). Since appropriate references are required for this, we recommend that this is
only carried out by the manufacturer.
WIKA operating instructions pressure switch, model PSD-3x
SP1 / C
SP2
+
4
2
Circular connector M12 x 1; 5-pin
Assignment
U
U -
S
+
+
1
3
5
EN
SP1 / C
SP2
4
2
21

Publicité

Table des Matières
loading

Table des Matières