Installation Check - Lenze ECSEE Serie Instructions De Montage

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

5

Installation check

5
Installation check
After completing the installation, check ...
The wiring for completeness, short circuit and earth fault.
ƒ
The power connection:
ƒ
Mains connection via terminals L1, L2, L3 (X21)
Connection of RFI filter / mains choke
Connection of brake resistor (internal/external) via terminals BR0, BR1
(X22)
Polarity of the DC−bus voltage supply via terminals +U
Control connection (X6):
ƒ
Supply of 24 V supply, GND
Thermal detector contact of external brake resistor or bridge if internal
brake resistor is used at terminals T1, T2.
Wiring adjusted to the signal assignment of the control terminals.
Communication via system bus (CAN).
ƒ
)
Note!
The next step is the commissioning. Relevant information can be
found in the detailed documentation of the power supply module.
ƒ
ƒ
86
Read the detailed documentation before switching on the power
supply module!
Perform the commissioning according to the instructions in the
detailed documentation!
l
, −U
(X22)
G
G
EDKCSEE040 DE/EN/FR 3.0

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Ecsee012Ecsee020Ecsee040

Table des Matières