Grounding The Generator; Operating Heavy Loads - Wacker Neuson GP2500A Manuel D'utilisation

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

GP
4.9

Grounding the Generator

Location
A ground connection (a) is located on the generator frame.
a
Function
This ground connection is used for electrically grounding the generator when
necessary to comply with the National Electrical Code and other federal, state, and
local regulations. For grounding requirements in your area, consult with a qualified
electrician, electrical inspector, or local agency having jurisdiction over electrical
compliance.
4.10

Operating Heavy Loads

Limit operations requiring the maximum rated output of 2600W to 20–30 minutes.
For continuous operation, do not exceed the continuous rated output of 2250W.
NOTICE: DO NOT exceed the current limit specified on the control panel for any
receptacle.
wc_tx004573gb.fm
If the generator is used at a construction site, there may be additional regula-
tions which must be observed.
In some areas, generators are required to be registered with local utility com-
panies.
There is a conductor between the generator (stator neutral winding) and the
frame.
wc_gr003951
33
Operation

Publicité

Table des Matières
loading

Table des Matières