10. First connection to the electric grid

This chapter details the process for the inverter's first connection to the grid.
First review the unit.

10.1. Unit inspection

You must check the correct condition of the installation before start-up.
Each installation is different, depending on its characteristics, the country in which it is located or other special
conditions which may apply. In all cases, before starting up, it is necessary to ensure that the installation complies
with the applicable legislation and regulations and that at least the part to be started up is complete.

10.1.1. Inspection

Before inverter's first connection to the grid, you must carry out a general inspection involving mainly:
Wiring inspection
Check that the cables are correctly joined to their connectors.
Check that these cables are in a good condition and that there are no hazards in their environment which
damage them, such as sources of intense heat, objects which could cut them or arrangements which put
them at risk of impacts or pulling.
Check the polarities of the DC and AC cables.
Review the unit's fastening
Check that the unit is secured firmly and is not at risk of falling.

10.1.2. Hermetic sealing of the unit

Ensure during installation operations that the unit's level of sealing has not been altered during connection of the
unit.
Check the correct adjustment of the connectors and that any cable grommets are well sealed.

10.2. Initial connection and configuration

Once the unit has been checked it needs to be connected to a smartphone or computer.
In order to feed the unit management, close its DC switch. After a few seconds the LEDs on the panel will light up,
once the unit management has power.
By default the inverter acts as a Wi-Fi access point, generating a SoftAP network with an SSID similar to Ingeteam_
xxMxxxxxxAxx_MMMM. From the moment the inverter is powered, the Wi-Fi network takes approximately one
minute to become operative.
Follow the instructions below to establish the connection and configure the inverter:
1.
From the device (smartphone or computer), search for the available Wi-Fi networks.
2.
Access the network created by the inverter with SSID Ingeteam_xxMxxxxxxAxx_MMMM. This network is
not password-protected.
3.
In the device's web browser, access address http://169.254.1.1/. If IP address 169.254.1.1 does not
work correctly, use address 192.168.10.3.
If a smartphone is used, depending on the model it may be required to disable mobile data first in order
to access IP 169.254.1.1.
4.
Follow the steps indicated in the basic configuration process for connecting via Wi-Fi or Ethernet.
5.
To finish the configuration of the communications, see section "11. Using the unit".
92
First connection to the electric grid
ABZ2011IQM01_C- Installation and Operation Manual