11. Installation / Commissioning checklist
Introduction
Examine the mechanical and electrical installation in accordance with this checklist to make sure that the
charging station is properly installed.
Checking the Installation
Examine the visual, mechanical and electrical installation when the charging station is un-pow-
ered.
CATEGORY
Overall look
Mechanical
installation
Electrical
installation
34 / 52
X
ITEM
You have received the ordered material.
You do not see any scratches or damages.
The charging station is fixed properly on the installation site.
Charging station's power supply capacity meets the electrical planning (cable
size, protective devices...).
Review the local electrical design plan.
The PE-cable screw is tight.
The power supply conductors (L1, L2, L3, N and PE) are properly connected.
The insulation of the power supply cable and the conductors (L1, L2, L3, N and
PE) is intact.
TN / TT network:
The voltage between PE and N is less than 10 V.
IT network:
The voltage between L1 and N is 230 V.
The voltage between L1 and PE is 130 V.
The PE conductor resistance is less than 3 Ω.
Test the functionality of the protective device.