Télécharger Imprimer la page

LEGRAND Green'up One Manuel D'installation page 31

Publicité

Les langues disponibles

Les langues disponibles

7. Mounting on concrete casting
Items needed:
Pedestal
Anchor bolts M12 (not included)
Washers (not included)
Nuts (not included)
Make sure that the materials used for the concrete casting and the installation procedures obey local building
regulations and safety standards.
Dig a trench for cable conduits and an excavation pit for the concrete foundation. The pit floor should be
compacted and level.
Put cable and possible drain pipes in place.
Fill the pit with concrete.
Let the concrete cure. Make sure that the surface stays level during the process.
Installation steps
1.
Make sure that the concrete surface is compacted and level.
2.
Drill a hole in the concrete for the anchor bolts. For more in-
formation, please see the anchor bolt instructions.
3.
Put the anchor bolts in place.
200
4.
Pull the electrical cables approx. 1600 mm measured from
the concrete surface.
5.
Attach the pedestal on the anchor bolts with washers and
nuts.
6.
Pull the electrical cables through the metal conduit in the
pole.
7.
Attach the charging station to the pedestal. See instruc-
tions on page 27.
Mounting Kit for EV Charging Station
LERAK136-FRENIT/20230502
1 pcs
4 pcs
31 / 52

Publicité

loading

Ce manuel est également adapté pour:

0 570 18