Complete The Installation - Kohler K-9393 Guide D'installation

Masquer les pouces Voir aussi pour K-9393:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

5. Install the Finished Wall
IMPORTANT! If the shower receptor is adjacent to vertical ducts or wiring, the shower receptor must be
surrounded with fire-rated, water-resistant wall material.
Install the wallboard with the factory edge (the paperbound edge) a minimum of 5/8" (15 mm)
above the finished, nailing-in flange threshold of the shower receptor.
Apply silicone sealant to the upper portion of the nailing-in flange where it will meet the
water-resistant wall material.
Ensure the front nailing-in flanges are similarly furred, and the wallboard is sealed to the nailing-in
flange.
Mud, tape, and finish the wallboard.
Seal the joints between the receptor rim and the finished wall with silicone sealant. RTV (Room
Temperature Vulcanizing) sealant is recommended.

6. Complete the Installation

NOTE: Refer to the sealant and/or putty manufacturer's instructions for proper application techniques.
Seal around the valving and outlets with silicone sealant or plumbers putty.
Install the shower door according to the manufacturer's instructions.
Install the finished floor.
Apply silicone sealant along the front edge of the receptor where it meets the floor.
Place the removable cover in the recessed area around the drain. Lightly push down on the
removable cover to secure the suction cups to the receptor.
1064933-2-C
Finished Wall
Check walls
for plumb.
Paperboard
Edge Down
Nailing-In Flange
Threshold
Removable
Cover
8
Wallboard
Furring Strip
5/8"
2x4
(1.6 cm)
Framing
Min
Galvanized
Screw/Nail
Silicone Sealant
Kohler Co.

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

K-9394K-9395K-9396K-9397K-9479

Table des Matières