Kohler K-11344 Guide D'installation Et D'entretien page 13

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

x4
10. Install the Bath
Turn the bath shell upside down on the saw horses.
Make sure all the drain connections are secure.
Cut the cable ties securing the PVC blower hose and keypad cable.
Position the shroud on the bath so the edges of the shroud rest inside the bath shell. Make sure the
blower hose and keypad cable are accessible from the bottom of the shroud.
Secure the shroud to the bath with a screw at each corner. Do not overtighten.
Make sure the foot clips are not in the locked position.
Lift the bath close to the installation location.
Cement the PVC blower hose connection to the PVC piping.
Route the keypad cable under the floor and to the blower motor area.
Carefully lift the bath into position while feeding the PVC pipe into the hole in the floor.
Make sure the posts on the bath frame fit into the four foot clips, and the drain fits into the drain
pipe.
Check for solid fit (no rocking) and a 24-1/8" (613 mm) rim corner height to the finished floor.
Lift and move the bath if needed, and adjust the four posts as needed to ensure a distance of
24-1/8" (613 mm) from the finished floor to the top of each bath rim corner. Adjust the levelers as
needed. Make sure the levelers and bath feet are tight.
Press down on the bath corners with your hand to make sure the bath does not move up and down,
or side to side. If the bath moves check that all four posts are inside the foot clips, and check that
the floor is level.
Kohler Co.
24-1/8"
(613 mm)
13
x4
x4
Post
x2
Bath
Leveler
1220597-2-D

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

K-14037

Table des Matières