7.4.2 Mounting the external
temperature sensor
The temperature sensor must be mounted in such a way that all
weather conditions are taken into consideration and the meas-
ured value is not falsified.
On the external wall of a heated room used as living space,
if possible on the north or north-west side of the building
Do not install in a "sheltered position" (e.g. in a wall niche or
under a balcony)
Not in the vicinity of windows, doors, exhaust air vents, ex-
ternal lighting or heat pumps
Not to be exposed to direct sunlight at any time of year
Sensor lead: Max. length 40 m; min. core cross-section
0.75 mm²; external diameter of the cable 4-8 mm.

7.4.3 Installing the strap-on sensor

It is only necessary to mount the strap-on sensors if they are in-
cluded in the scope of supply of the heat pump but have not yet
been installed.
The strap-on sensors can be fitted as pipe-mounted sensors or
installed in the immersion sleeve of the compact manifold.
Mounting as a pipe-mounted sensor
Remove paint, rust and scale from heating pipe.
Coat the cleaned surface with heat transfer compound
(apply sparingly).
Attach the sensor with a hose clip (tighten firmly, as loose
sensors can cause malfunctions) and thermally insulate.
7.4.4 Hydraulic distribution system
The compact manifold and the dual differential pressureless
manifold function as an interface between the heat pump, the
heating distribution system, the buffer tank and, in some cases,
even the hot water cylinder. A compact system is used to simplify
the installation process, so that a lot of different components do
not have to be installed individually. Further information can be
found in the relevant installation instructions.
Compact manifold
The return sensor can remain in the heat pump, or should be in-
stalled in the immersion sleeve. The remaining empty space be-
tween the sensor and the immersion sleeve must be filled com-
pletely with heat transfer compound.
dual differential pressureless manifold
In order for the heating circuit pumps of the generator and con-
sumer circuits to supply the flow to the return sensor, this must
be installed in the immersion sleeve of the dual differential pres-
sureless manifold.
www.dimplex.de

7.5 Electrical connection

7.5.1 General
All electrical connection work must be carried out by a trained
electrician or a specialist for the specified tasks in accordance
with the
installation and operating instructions,
country-specific installation regulations (e.g. VDE 0100),
technical connection conditions of the energy suppliers and
supply grid operators (e.g. TAB) and
local conditions.
To ensure that the frost protection function of the heat pump
works properly, the heat pump manager must remain connected
to the power supply and the flow must be maintained through the
heat pump at all times.
The switching contacts of the output relay are interference-sup-
pressed. Therefore, depending on the internal resistance of the
measuring instrument, a voltage can also be measured when the
contacts are open. However, this will be much lower than the line
voltage.
Extra-low voltage is connected to controller terminals N1-J1 to
N1-J11; N1-J19; N1-J20; N1-J23 to N1-J26 and terminal strip
X3; X5.1. If, due to a wiring error, the line voltage is mistakenly
connected to these terminals, the heat pump manager will be de-
stroyed

7.5.2 Electrical installation

1)
The supply electric cable for the output section of the heat
pump (up to 4-core) is fed from the electricity meter of the
heat pump via the utility blocking contactor (if required) into
the heat pump Connection of the mains cable to the control
panel of the heat pump via terminal X1: L1/L2/L3/PE.
An all-pole disconnecting device with a contact gap of at
least 3 mm (e.g. utility blocking contactor or power contac-
tor) and an all-pole circuit breaker with common tripping for
all external conductors must be installed in the power supply
for the heat pump (tripping current and characteristic in com-
pliance with the device information).
ATTENTION!
Ensure that there is a clockwise rotating field: With incorrect wiring the
starting of the heat pump is prevented. A corresponding warning is
indicated on the display of the heat pump manager (adjust wiring).
2)
The three-core electric supply cable for the heat pump man-
ager (heating controller N1) is fed into the heat pump .
Connection of the control line to the control panel of the heat
pump via terminal X2: L/N/PE.
Details on the power consumption of the heat pump are
listed on both the product information sheet and the type
plate.
The (L/N/PE~230 V, 50 Hz) supply cable for the heat pump
manager must have a constant voltage. For this reason, it
should be tapped upstream from the utility blocking contac-
tor or be connected to the household current, as important
protection functions could otherwise be lost during a utility
block.
452235.66.05 · FD 9310
SI 6TU - SI 18TU
EN-7

Publicité

Chapitres

Table des Matières
loading

Ce manuel est également adapté pour:

Si 8tuSi 11tuSi 14tuSi 18 tu

Table des Matières