Action
All packing materials and restraints are removed from each cabinet.
Each cabinet in the UPS system is placed in its installed location.
A cabinet grounding kit / mounting kit is installed between any cabinets that are bolted
together.
All conduits and cables are properly routed to the UPS and any ancillary cabinets.
All power cables are properly sized and terminated.
Neutral conductors are installed and bonded to ground according to the requirements.
A ground conductor is properly installed.
Battery cables are terminated and connected to battery connectors.
Battery Shunt trip and Aux contact signal wiring is connected from the UPS to the battery
breaker.
LAN drops are installed.
All LAN connections are completed.
Air conditioning equipment is installed and operating correctly.
The area around the installed UPS system is clean and dust-free (it is recommended that
the UPS is installed on a level floor suitable for computer or electronic equipment).
There is adequate workspace around the UPS and other cabinets.
Adequate lighting is provided around all the UPS equipment.
A 230 VAC service outlet is located within 7.5 meters of the UPS equipment.
The Remote Emergency Power-off (REPO) device is mounted in its installed location
and its wiring is terminated inside the UPS cabinet.
If EPO is used in the NC configuration, a jumper is installed on the EPO between pins 1
and 2.
(OPTIONAL) Alarm relays and signal outputs are wired appropriately.
(OPTIONAL) A remote battery disconnect control is mounted in its installed location and
its wiring is terminated inside the UPS and battery cabinet.
(OPTIONAL) Accessories are mounted in their installed locations and their wiring is
terminated inside the UPS cabinet.
Start-up and operational checks are done by an authorized Eaton Customer Service
Engineer or by a qualified service engineer authorized by Eaton.
The unpacking and unloading of the UPS is shown in illustrations 14.1-14.8.
Before you start to unpack and unload the UPS, examine the TipNTell and DropNTell
indicators on the package surface. If the equipment has been correctly transported in the
upright position, the indicators should be intact. If the TipNTell indicator arrow has turned
all blue or the arrow head(s) of the DropNTell indicator are black, contact the appropriate
parties to report inappropriate transportation.
For transportation purposes, the UPS cabinet is bolted onto a wooden pallet. Before you
unload the cabinet from the pallet, use a forklift or other material handling equipment to
move the cabinet to the installation area.
EN
Yes/No
7