Battery drawers
There are two different procedures for installing/replacing battery
drawers inside UPS Trimod® and UPS BATTERY Trimod®.
Carefully read all instructions before operating on the equipment.
The drawers batteries must always be added/replaced in multiples
of 4 (1 KB).
Note: if the installation/replacement has changed the total number of
KB installed in the UPS, you must update the number of KB via the
front panel.
After completing the procedure above described, we recommand
to calibrate batteries in order to get correct informations about UPS
runtime.
If the UPS has more than 1 KB for each 10kVA output power, you can
replace 1 KB at a time with UPS Online.
This operation can be done inside UPS Trimod® and/or UPS
BATTERY Trimod®.
Remember that 1 KB consists of 4 battery drawers.
The replacement procedure is as follows:
1. Make sure the UPS has installed at least every 1KB 10kVA output
power output plus one;
2. Make sure the UPS is not operating on battery and the charger is
maintenance or standby state. To check the status of the charger,
enter the state ups -> Measures -> batteries, and check the fourth
item shown on the display.
3. Remove the four battery drawers (n° 1KB).
4. Insert the new 4 batteries drawers and secure them with the screws
provided;
5. Repeat steps 2, 3 and 4 for each KB to install/replace.
In the case of simple addition of KB is enough to follow the steps 2, 4
and 5.
uPS Trimod® BATTERY Recommended Battery Fuse Ratings
POWER
10/15/20/30/40/60 kVA
uPS Trimod® BATTERY/2 Recommended Battery Fuse Ratings
POWER
10/15/20/30/40/60 kVA
uPS Trimod® BATTERY (1x94Ah) Recommended Battery Fuse Ratings
POWER
10 kVA
15/20 kVA
30 kVA TT/TM
40 kVA
60 kVA
All manuals and user guides at all-guides.com
f B+
N.4 - 50A 500V gg (14 x 51)
f B+
N.5 - 50A 500V gg (14 x 51)
Trimod® BATTERY (1x94Ah)
f B+
N.1 - 50A 500V gg (22 x 58)
N.1 - 100A 500V gg (22 x 58)
N.2 - 80A 500V gg (22 x 58)
N.2 - 125A 500V gg (22 x 58)
N.3 - 100A 500V gg (22 x 58)
4
WARNING
Always replace only 1 KB at a time
Note: If the UPS switches to battery while you are performing the
operation, stop and do not remove or insert battery drawers! it is
possible to resume operation when the UPS returns to work on-line.
Note: if during the operation mains is missing, you will have a reduced
autonomy: you should therefore carefully consider such cases in
relation to the application before starting.
Installation / replacement battery drawers in uPS maintenance
bypass
This procedure applies to each model of UPS Trimod® and UPS
BATTERY Trimod®.
WARNING
In maintenance bypass the load is powered directly from the
mains input.
1. To bring the UPS in maintenance bypass mode follow steps 1 to 8
described in paragraph 9.3.1.
2. Remove the four battery drawers (n° 1KB).
To add another KB (if there is enough space available) does not
remove any battery drawer;
3. Insert the new four batteries drawers and secure with the screws
provided;
4. Repeat steps 2 and 3 for each KB to install / replace.
5. follow steps 1 to 6 described in section 9.4.2 to bring state of the
UPS maintenance bypass switch to the On-line.
In the case of simple addition of KB is sufficient to perform the steps
described in paragraphs 1, 3, 4 and 5.
BATTERY FuSE
Trimod® BATTERY 4KB
N.4 - 50A 500V gg (14 x 51)
BATTERY FuSE
Trimod® BATTERY/2 5KB
N.5 - 50A 500V gg (14 x 51)
BATTERY FuSE
N.1 - 50A 500V gg (22 x 58)
N.1 - 100A 500V gg (22 x 58)
N.2 - 80A 500V gg (22 x 58)
N.2 - 125A 500V gg (22 x 58)
N.3 - 100A 500V gg (22 x 58)
f B-
f B-
f B-