Start-up, calibration and operation of the burner

6.1

Notes on safety for the first start-up

The first start-up of the burner must be carried out
by qualified personnel, as indicated in this manual
and in compliance with the standards and
regulations of the laws in force.
ATTENTION
Check the correct working of the adjustment,
command and safety devices.
ATTENTION
6.2

Adjustments prior to ignition

 The following adjustments must be carried out:
 Open the manual valves upstream of the gas train.
 Bleed the air from the gas line using the screw on the socket
START.
6.3

Burner start-up

Close the thermostat and switch on the burner's power.
The burner starts up under pre-purging conditions to the START
and the ignition occurs.
If the fan starts up, but no flame appears by the end of the safety
time, the control box allows the start-up programme to be
repeated up to 2 times.
6.4

Fan adjustment

Modulation is based on variable-speed technology.
Combustion air delivery can be adjusted by varying the motor's
speed (rpm).
The proportioning gas train delivers the right amount of fuel,
depending on the pressure detected in the purging circuit.
Hence the output delivered is adjusted by varying the motor's
speed of rotation.
The speed of the motor can be adjusted by means of three
"Trimmers" (Fig. 11).
20144769
Start-up, calibration and operation of the burner
Before starting up the burner, refer to section
"Safety test - with no gas supply" on page 24.
ATTENTION
 Check the trimmer settings on the control box (Fig. 11).
If ignition does not occur upon the third attempt, the burner goes
into lockout mode. Reset and wait for a new start-up attempt.
If ignition is still not achieved, it may be that gas is not reaching
the combustion head within the safety time period of 5 seconds.
Turn the screw V1 on the gas valve mixer slightly anticlockwise.
Once ignition has taken place, proceed with burner global
calibration operations.
18
GB
D10762
Fig. 11