INITIAL COMMISSIONING

5
Initial Commissioning
1. Set the special tool (1) down on a
stable work surface.
2. Bolt the mounting plate firmly at all 4
corners (2) to a worktop.
3. Connect the compressed air connection
(1) of the foot switch to an external
compressed air system (2). The input
air pressure of the external compressed
air system must not be less than 8 bar
and must not exceed 10 bar.
The special tool is ready for use.
®
32
The special tool is prepared as standard for the direct
connection to an external compressed air system.
Ensure that the coupling sleeve on the coupling connector
locks into place.
Fig. 8
Fig. 9