INSTALLATIoN

Check the installation space ensures the minimum space indicated can be maintained.
FIRST SWITCH-ON
Qualify the installation according to the following test table:
– Vacuum test
– Automatic control test
– Verification of the measuring instrumentsof the sterilizer
– Overheat cutout test
– Thermometric test for small load (*)
– Small load dryness test (*)
– Steam penetration test for porous loads (*)
– Thermometric test for solid load (*)
– Solid load dryness test (*)
– Steam penetration test for solid loads (*)
– Thermometric tests (load selectedon user requirements)
– Microbiological tests (load selectedon user requirements)
(*)To be carried outwithcyclesof 121°Cand 134°C
The door has the following open dimensions:
40
THE DEVICE MUST BE INSTALLED By SPECIALIST
TECHNICIANS.
660
660 (16) - 760 (21)
410
410 (16) - 470 (21)
521
520 (16) - 580 (21)
MODEL SIZES 16-21
30
20
421
450
20
403
408