Install 1/2-in. liquid-tight flexible conduit to the conduit
stand pipe.
NOTE: Consult national and local codes for approved, liquid-
tight flexible conduit.
9.
Place the bollard on its side.
10. Gently guide the conduit through the bottom of the bollard
and position the bollard over the bolts and onto the base.
11. Use a level on two sides (90° apart) of the bollard to check
whether the bollard is standing straight.
12. If the bollard is not plum and level, remove the bollard and
place washers on the lag bolts as needed to level the bollard.
13. Repeat Steps 7 and 8 until the bollard is level.
NOTE: Alternately, double-nut leveling installation is accept-
able.
Bosch Automotive Service Solutions Inc.
Power Xpress™ Bollard Charge Station Installation Guide | 7 | en
14. Install a washer, lock washer, and nut on each bolt.
15. Tighten the nuts evenly around the bollard. Any gap be-
tween the bollard base and the mounting surface may be
filled with caulk suitable for the installation environment
16. Position the conduit on the left side of the bollard (opposite
the open metal slot side).
578988 | REV. A | 28.10.2016