12 Commissioning

12.1 General information on using MPS systems and stations

The systems and stations of the MPS are normally delivered in the following state:
Fully assembled
Individually adjusted and ready for use
Pre-commissioned
Tested
Commissioning is normally limited to visual inspection in order to ensure correct tubing connections, wiring
and operating voltage supply.
All components, tubing connections and cabling are clearly identified, so that all of the connections can be
readily restored as required.

12.2 Mechanical commissioning

If the Distributing Pro and Joining stations are operated with other downstream stations, the stoppers at the
end of the conveyor module have to be removed.
Setup as individual station,
the stopper at the end of the conveyor is mounted
42
When stations are combined, the mechanical setup, as well as sensor positions and
settings, may have to be changed.
Setup with downstream station,
the stopper at the end of the conveyor is removed