Check and carry out commissioning

D ATTENTION!
Risk of disruptions due to moisture in the device!
If the device is moved from a cold environment into a hot
one, condensation may form inside.
☞ Wait about 2-3 hours before bringing the device into
service.
☞ Check that the mains plug is freely accessible.
☞ Check that the mains cable and the electrical connection
cable are not kinked, crushed or damaged.
☞ Ensure that air outlets are not closed or covered.
☞ Make sure that the ventilation slots are free.
☞ Check the correct functioning of the device.
D "4. Operation" (page 104).